How it works
How to get house plans drawn for your lot.
You bring the lot and what you want to build. We turn it into a coordinated plan set, drafted in Revit and sealed by licensed engineers, 15 business days after your project starts. Here is every step, and who does what.
At a glance
Your schedule gets drawn before your plans.
- Before day 1
Scope and fixed quote
Tell us what you want to build. We confirm the scope, the fee and your delivery date.
- Day 1
Reserved start
Once the agreement, deposit and survey are in, the 3 week clock starts.
- Days 3 to 5
Design review
Review floor plans and 3D views, with your builder if you like, and we lock the layout.
- Days 6 to 14
Coordination and seals
The full set, engineering and energy calculations run in parallel, then a final quality check.
- Day 15
Delivery
PDF set, Revit model, CAD files and images, about 3 weeks after you start.
15 business days, about 3 weeks, from reserved start to delivery
Step by step
From your first message to your permit.
-
Before day 1
Tell us what you want to build
Send the request form with your city and county, the type and size of the project, when you want design to start and what you already have. A survey, a sketch, phone photos or a floor plan you like all help, but you can ask for a quote before you have everything.
We confirm the scope, the fixed fee and your delivery date in writing. Your quote lists every file, image, review and revision round before production starts, so nothing changes at delivery.
Bringing a floor plan you like is the fastest way to your permit set and keeps your price at the low end. We use it to understand the layout you want, then draw your own plans for your lot.
YouDashline
-
Day 1
Reserve your start
Your 15 business days start on your reserved start date, once three things are in:
- The signed agreement with your scope and fixed price
- The deposit
- A current boundary survey, with spot elevations if your site needs them
The survey gives us the shape of the lot, its grades and what already sits on it. A soil report comes in only if your engineer or county asks for one. The clock starts on your reserved start date, not when you send the form.
YouDashline
-
Days 3 to 5
Design review
You review the floor plans and 3D views of your home, with your builder if you like, and we lock the layout together. This is the moment for changes to rooms, walls, windows and the shape of the roof.
A structural change after the first design review restarts the schedule, because the engineering and every sheet after it depend on the layout you lock here.
YouYour builderDashline
-
Days 6 to 14
Coordination and seals
With the layout locked, the full plan set, the engineering and the Florida energy code calculations run in parallel. The set covers the site plan, floor plans, elevations, sections, roof plan and details, plus the other sheets your package includes.
Licensed engineers review and seal the disciplines in your package, and the whole set gets a final quality check before it leaves.
What each sheet in a plan set is for
DashlineLicensed engineers
-
Day 15
Delivery
You receive the PDF plan set, the Revit model, CAD files in the formats your builder or consultants need, and the images listed in your quote, about 3 weeks after your project starts.
DashlineYou
-
After delivery
Your building permit
The plan set goes to your city or county building department with the permit application. Permit review runs on the department's own schedule and is not part of the 15 business days.
Survey, soil report and permit fees are separate from our price. If your site needs anything extra, we tell you before you commit.
You or your builderBuilding department
Who does what
Everyone knows their part before day 1.
Tell us who will use the drawings and what they need. We agree on file formats, documentation and coordination as part of your scope.
| Who | Their part |
|---|---|
| YOU | YouTell us what you want to build, send the survey and make the design decisions at the first review. |
| GC | Your builderJoins the design review if you like and gets the files in the formats they need. |
| DL | DashlineDraws the set in Revit, runs the engineering and energy calculations, checks the set and delivers the files. |
| SEAL | Licensed engineersReview and seal the disciplines in your package. |
| BD | Building departmentReviews the permit application on its own schedule. |
Getting started
What we need from you.
To get a quote
- Project city and county
- Project type and approximate size
- A floor plan you like, if you have one
- Your requirements and style
- When you want design to start
- Your name, email and phone
To start production
- Signed scope and fixed price
- Deposit
- Reserved start date
- Current boundary survey, with spot elevations if your site needs them
- Soil report, if your engineer or county asks for one
- Your design decisions at the first review
Questions about permits, prices and timing The plans we draw
Ready to see your plans drawn?
Share your requirements, timing and files. Next comes a clear scope, a fixed quote and a delivery date.